A. 4
B. 9.6
C. 9
D. 10
Part of work completed by A and B in 4 days
= 4*((1/16) + (1/12))
= 7/12 C can complete 5/12th of the work in 4 days C can complete the whole job in
4÷(5/12) = 9.6 days
Related Mcqs:
- Two pipes can fill a tank in 10 hrs. and 12 hrs. respectively while a third pipe empties the full tank in 20 hrs. If all the three pipes operate together , in how much time the tank will be filled ?
- A. 7.5 hrs B. 5 hrs C. 7 hrs D. None of these...
- If 6 men working together can complete 50 identical tasks in 4 hours then how many such identical tasks can be completed if 10 men are working together for 6 hours?
- A. 20 B. 25 C. 125 D. 60...
- 12 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be needed to fill the same tank, if the capacity of each bucket is 9 litres?
- A. 14 B. 15 C. 16 D. 18...
- Mansoor-Ul-Haque and Aaqib are working on a special assignment. Mansoor-Ul-Haque needs 6 hours to type 32 pages on a computer and Aaqib needs 5 hours to type 40 pages. If both of them work together on two different computers, how much time is needed to type an assignment of 110 pages?
- A. 7 hour 15 minutes B. 7 hour 30 minutes C. 8 hour 15 minutes D. 8 hour 30 minutes...
Recent Comments