Which one of the following is not an Umbrella Activity that complements the five process framework activities and help team manage and control progress, quality, change, and risk ?

A. Reusability management
B. Risk management
C. Measurement
D. User Reviews

Leave a Reply

Your email address will not be published. Required fields are marked *