A. LOC
B. FP
C. Fuzzy Logic
D. LOC and FP
Explanation: A function point (FP) is a unit of measurement to express the amount of business functionality an information system provides to a user
Related Mcqs:
- The environment that supports the software project is called_______________________?
- A. CLSS B. SEE C. FAST D. CBSE...
- Which version of COCOMO states that once requirements have been stabilized, the basic software architecture has been established ?
- A. Early design stage model B. Post-architecture-stage model C. Application composition model D. All of the mentioned...
- Why is decomposition technique required ?
- A. Software project estimation is a form of problem solving B. Developing a cost and effort estimate for a software project is too complex C. All of the mentioned D. None of the mentioned...
- Which software engineering team has no permanent leader ?
- A. Controlled decentralized (CD) B. Democratic decentralized (DD) C. Controlled Centralized (CC) D. None of the mentioned...
- What is the recommended distribution of effort for a project ?
- A. 40-20-40 B. 50-20-30 C. 30-40-30 D. 50-30-20...