A. 14
B. 16
C. 15
D. 11
Work done by Kamal in 1 day = 1/20
Work done by Suresh in 1 day = (1/20) × (125/100) = 5/80 = 1/16
=> Suresh can complete the work in 16 days
Related Mcqs:
- A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately. If A begins first, in how many days the work will be completed ?
- A. 42/4 days B. 41/4 days C. 55 days D. None of these...
- 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.
- A. 4 days B. 6 days C. 2 days D. 8 days...
- Running at the same constant rate, 6 identical machines can produce a total of 270 bottles per minute. At this rate, how many bottles could 10 such machines produce in 4 minutes?
- A. 2700 B. 1080 C. 450 D. 1800...
- Mansoor-Ul-Haque and Aaqib are working on a special assignment. Mansoor-Ul-Haque needs 6 hours to type 32 pages on a computer and Aaqib needs 5 hours to type 40 pages. If both of them work together on two different computers, how much time is needed to type an assignment of 110 pages?
- A. 7 hour 15 minutes B. 7 hour 30 minutes C. 8 hour 15 minutes D. 8 hour 30 minutes...
- Two taps X and Y can fill a tank in 10 hrs. and 15 hrs.respectively. If the both taps are opened together, the tank will be full in_________?
- A. 3 hrs. B. 4 hrs, C. 5 hrs. D. 6 hrs....
Recent Comments