.Management Sciences
A. 50
B. 30
C. 40
D. 13
Work done by 4 men and 6 women in 1 day = 1/8
Work done by 3 men and 7 women in 1 day = 1/10
Let 1 man does m work in 1 day and 1 woman does w work in 1 day. The above equations can be written as
4m + 6w = 1/8 —(1)
3m + 7w = 1/10 —(2)
Solving equation (1) and (2) , we get m=11/400 and w=1/400
Amount of work 10 women can do in a day = 10 × (1/400) = 1/40
Ie, 10 women can complete the work in 40 days
Related Mcqs:
- A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every Third day ?
- A. 12 days B. 15 days C. 16 days D. 18 days...
- 2 men and 12 women can finish a job in 4 days. 4 men and 6 women can do the same job in 5 days. Find the time taken by 1 man and 1 woman to complete the job.
- A. 30 days B. 25 days C. 24 days D. 20 days...
- If 10 bulls can plough 20 identical fields in 3 days working 10 hours a day, then in how many days can 30 bulls plough 32 same identical fields working 8 hours a day?
- A. 2 B. 8 C. 10 D. 12...
- Two pipes P and Q can fill a cistern in 12 min. and 15 min. respectively but a third pipe ‘R’ can empty the full tank in 6 min. P and Q are kept open for 5 min. in the beginning and then ‘R’ is also opened. In what time is the cistern emptied ?
- A. 30 min B. 35 min C. 40 min D. 45 min...
- P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
- A. 7 B. 8 C. 9 D. 6 Let P takes x days to complete the work Then Q takes x/2 days and R takes x/3 days to finish the work Amount of work P does in 1 day = 1/x Amount of work Q does in 1 day = 2/x Amount of work R does in 1 day … P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish...
Recent Comments