10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?

A. 7
B. 5
C. 6
D. 4

Work done by 10 men in 1 day = 1/7
Work done by 1 man in 1 day = (1/7)/10 = 1/70
Work done by 10 women in 1 day = 1/14
Work done by 1 woman in 1 day = 1/140
Work done by 5 men and 10 women in 1 day = 5 × (1/70) + 10 × (1/140)
= 5/70 + 10/140 = 1/7
=> 5 men and 10 women can complete the work in 7 days