P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
0
A. 7
B. 8
C. 9
D. 6
Let P takes x days to complete the work
Then Q takes x/2 days and R takes x/3 days to finish the work
Amount of work P does in 1 day = 1/x
Amount of work Q does in 1 day = 2/x
Amount of work R does in 1 day = 3/x
Amount of work P,Q and R do in 1 day = 1/x + 2/x + 3/x = 1/x (1 + 2 + 3) = 6/x
6/x = 2
=> x = 12
=> Q takes 12/2 days = 6 days to complete the work
If 28 men can finish a work in 15 days, 21 men can finish the same work in___________?
A. 24 days
B. 14 days
C. 15 days
D. 20 days
(more…)
A is thrice as good as B in work. A is able to finish a job in 60 days less than B. They can finish the work in___________days if they work together.
A. 18 days
B. 22 ½ days
C. 24 days
D. 26 days
(more…)
A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
A. 4(2/3) days
B. 4 days
C. 5(1/3) days
D. 1(1/3) days
(more…)