If 28 men can finish a work in 15 days, 21 men can finish the same work in___________?
A. 24 days
B. 14 days
C. 15 days
D. 20 days
(more…)
A is thrice as good as B in work. A is able to finish a job in 60 days less than B. They can finish the work in___________days if they work together.
A. 18 days
B. 22 ½ days
C. 24 days
D. 26 days
(more…)
A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
A. 4(2/3) days
B. 4 days
C. 5(1/3) days
D. 1(1/3) days
(more…)
A can do (1/3) of a work in 5 days and B can do (2/5) of the work in 10 days. In how many days both A and B together can do the work ?
A. 75/8 days
B. 44/6 days
C. 48/5 days
D. None of these