Category: Time and Work Mcqs
4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
A. 15 days
B. 10 days
C. 8 days
D. 20 days
(more…)
A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
A. 35 Rs.
B. 40 Rs.
C. 45 Rs.
D. None of these
(more…)
P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?
A. 9(3/5) days
B. 9(1/5) days
C. 9(2/5) days
D. 10 days
(more…)
P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
A. 7
B. 8
C. 9
D. 6
Let P takes x days to complete the work
Then Q takes x/2 days and R takes x/3 days to finish the work
Amount of work P does in 1 day = 1/x
Amount of work Q does in 1 day = 2/x
Amount of work R does in 1 day = 3/x
Amount of work P,Q and R do in 1 day = 1/x + 2/x + 3/x = 1/x (1 + 2 + 3) = 6/x
6/x = 2
=> x = 12
=> Q takes 12/2 days = 6 days to complete the work