The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is_______________?
A. Rs. 400
B. Rs. 425
C. Rs. 450
D. Rs. 500
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is__________________?
A. 500 m3
B. 1000 m 3
C. 1500 m3
D. 2000 m3
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3
The measurement is made in square metre in case of_________________?
A. Cement concrete in foundation
B. R.C.C. structure
C. Hollow concrete block wall
D. None of these
For the construction of buildings, the subheads of the estimate are________________?
A. Earthwork, Concrete work, Brick work
B. Brickwork, Stone work, Roofing
C. Brickwork Flooring, Wood work, Steel work
D. All the above
The expected out turn of 12 mm plastering with cement mortar is_______________?
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
The item of the brick structure measured in sq.m, is___________________?
A. Reinforced brick work
B. Broken glass coping
C. Brick edging
D. Brick work in arches
Anti-siphonage pipe is connected to__________________?
A. Main soil pipe
B. Bottom of P trap W.C.
C. Top of P trap W.C.
D. Side of water closet
The plinth area of a building not includes_________________?
A. Area of the walls at the floor level
B. Internal shaft for sanitary installations up to 2 sq m. in area
C. Lift and wall including landing
D. Area of cantilevered porch
The ‘centre line method’ is specially adopted for estimating_________________?
A. Circular buildings
B. Hexagonal buildings
C. Octagonal buildings
D. All the above