A. Cement concrete in foundation
B. R.C.C. structure
C. Hollow concrete block wall
D. None of these
Related Mcqs:
- While estimating the qualities for the construction of a building, the correct metric unit is________________?
- A. Metre for length B. Cubic metre for area C. Square metres for volume D. Litre for capacity...
- If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by_______________?
- A. Mid-section formula B. Trapezoidal formula C. Prismoidal formula D. All the above...
- Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds_________________?
- A. 2.0 % B. 2.5 % C. 4.0 % D. 5.0 %...
- Pick up the item of work not included in the plinth area estimate______________?
- A. Wall thickness B. Room area C. W.C. area D. Courtyard area...
- The expected out turn of half brick partition wall per mason per day is___________________?
- A. 1.5 m 3 B. 2.0 m3 C. 4.0 m2 D. 5.0 m2...