.Management Sciences
A. 30 days
B. 25 days
C. 24 days
D. 20 days
Part of work done by 1 man in a day = 1/m Part of work done by 1 woman in a day
= 1/w (2/m)+(12/w) = (1/4) (4/m)+(6/w) = (1/5) Solving,
1/m = 1/40 ,1/w = 1/60 (1/m)+(1/w) = 5/120 = 1/24