A. 32 hours
B. 48 hours
C. 3 days
D. 4 days
Part of task completed by A in a day = 1/x Part of task completed by B in a day = 3/x (B is thrice as efficient as A) (1/x)+(3/x) = 1 4/x = 1 x = 4 B completes 3/4th of the task in a day. He takes 4/3 days to complete the entire task. 4/3 days = (4/3*24) hours = 32 hours