A. It defines tasks required to define resources, timelines, and other project related information
B. It defines a set of negotiation activities at the beginning of each pass around the spiral
C. It defines tasks required to assess both technical and management risks
D. It defines tasks required to construct, test, install, and provide user support
Explanation: Except option “b” all other tasks/activities are present in Spiral Model as well.
Related Mcqs:
- What is the major advantage of using Incremental Model ?
- A. Customer can respond to each increment B. Easier to test and debug C. It is used when there is a need to get a product to the market early D. Easier to test and debug & It is used when there is a need to get a product to the market early...
- A company is developing an advance version of their current software available in the market, what model approach would they prefer ?
- A. RAD B. Iterative Enhancement C. Both RAD & Iterative Enhancement D. Spiral...
- Identify the disadvantage of Spiral Model?
- A. Doesn’t work well for smaller projects B. High amount of risk analysis C. Strong approval and documentation control D. Additional Functionality can be added at a later date...
- Purpose of process is to deliver software ___________________?
- A. in time B. with acceptable quality C. that is cost efficient D. both in time & with acceptable quality...
Recent Comments