Which software project sizing approach develop estimates of the information domain characteristics ?
A. Function point sizing
B. Change sizing
C. Standard component sizing
D. Fuzzy logic sizing
Related Mcqs:
- Which of the following is not achieved by an automated estimation tools ?
- A. Predicting staffing levels B. Predicting software cost C. Predicting software schedules D. Predicting clients demands...
- Which technique is applicable when other projects in the same analogy application domain have been completed ?
- A. Algorithmic cost modelling B. Expert judgement C. Estimation by analogy D. Parkinson’s Law...
- Which risks are associated with constraints imposed by management or the marketplace ?
- A. Business impact risks B. Process definition risks C. Product size risks D. Development environment risks...
- PM-CMM stands for___________________?
- A. people management capability maturity model B. process management capability maturity model C. product management capability maturity model D. project management capability maturity model...
- What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
- A. Degree of Rigor B. Adaptation criteria C. Task Set D. Both degree of Rigor and adaptation criteria...