.Management Sciences
A. Performance risk
B. Cost risk
C. Support risk
D. Schedule risk
Related Mcqs:
- Which model is used during early stages of the system design after the requirements have been established ?
- A. An application-composition model B. A post-architecture model C. A reuse model D. An early design model...
- Which of the following risk is the failure of a purchased component to perform as expected ?
- A. Product risk B. Project risk C. Business risk D. Programming risk...
- Which of the following is not an approach to software cost estimation ?
- A. Empirical B. Heuristic C. Analytical D. Critical...
- Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition ?
- A. External inputs B. External outputs C. External process D. External inquiries...
- What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
- A. Degree of Rigor B. Adaptation criteria C. Task Set D. Both degree of Rigor and adaptation criteria...
Recent Comments