.Management Sciences
A. PERT
B. CPM
C. CMM
D. Both PERT and CPM
Explanation: Program evaluation and review technique (PERT) and critical path method (CPM) are two project scheduling methods that can be applied to software development.
Related Mcqs:
- COCOMO was developed initially by _____________________ ?
- A. B.Beizer B. Rajiv Gupta C. B.W.Bohem D. Gregg Rothermal...
- Which of the following strategies means that the impact of the risk will be reduced ?
- A. Avoidance strategies B. Minimization strategies C. Contingency plans D. All of the mentioned...
- Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks ?
- A. Software Macroscopic schedule B. Software Project scheduling C. Software Detailed schedule D. None of the mentioned...
- A make-buy decision is based on whether________________?
- A. The software may be purchased off-the-shelf B. “Full-experience” or “Partial-experience” software components should be used C. Customer-built software should be developed D. All of the mentioned...
- Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system ?
- A. System building B. Release management C. Change management D. Version management...
Recent Comments