If a Direct approach to software project sizing is taken, size can be measured in__________________?
A. LOC
B. FP
C. LOC and FP
D. None of the mentioned
Explanation: LOC or Line of Code is a direct measure to estimate project size.
Related Mcqs:
- Which of the following is not considered as a risk in project management ?
- A. Specification delays B. Product competition C. Testing D. Staff turnover...
- CLSS stands for_____________________?
- A. conveyor line sorting system B. conveyor line sorting software C. conveyor line sorting speed D. conveyor line sorting specification...
- Which risks are associated with the overall size of the software to be built or modified ?
- A. Business impact risks B. Process definition risks C. Product size risks D. Development environment risks...
- Who defines the business issues that often have significant influence on the project ?
- A. Practitioners B. Project managers C. Senior managers D. None of the mentioned...
- Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as ________________?
- A. Time Allocation B. Effort Validation C. Defined Milestone D. Effort Distribution...
Recent Comments