.Management Sciences
A. duration
B. total float
C. free float
D. interfering float
E. none of the above
Related Mcqs:
- Routing prescribes the_________________?
- A. flow of material in the plant B. proper utilization of man power C. proper utilization of machines D. inspection of final product E. none of the above...
- The objective of time study is to determine the time required to complete a job by_______________?
- A. fast worker B. average worker C. slow worker D. new entrant E. any one of the above...
- Work study is concerned with_________________?
- A. improving present method and finding standard time B. motivation of workers C. improving production capability D. improving production planning and control E. all of the above...
- Slack of various events on the critical path in PERT/CPM chart___________________?
- A. increases continuously B. decreases continuously C. remains constant D. may increase or decrease depending on various factors E. unpredictable...
- In A-B-C control policy, maximum attention is given to__________________?
- A. those items which consume money B. those items which are not readily available C. those x items which are in more demand D. those items which consume more money E. proper quality assurance program-mes...
Recent Comments