.Management Sciences
A. bar chart method
B. milestone chart
C. critical path method (CPM)
D. programme evaluation and review technique (PERT)
E. none of the above
Related Mcqs:
- Product layout is employed for____________________?
- A. batch production B. continuous production C. effective utilization of machine D. all of the above E. none of the above...
- Acceptance sampling is widely used in________________?
- A. batch production B. job production C. mass production D. all of the above E. none of the above...
- Which of the following layouts is suited for mass production_________________?
- A. process layout B. product layout C. fixed position layout D. plant layout E. functional layout...
- PMTP (predetermined motion time systems) include___________________?
- A. MTM (method time measurement) B. WFS (work factor systems) C. BNTS (basic motion time study) D. all of the above E. none of the above...
- The reasons which are basically responsible for the formation of a queue should be that ___________________?
- A. the average service rate Hess than the average arrival rate B. output rate is linearly proportional to input C. output rate is constant and the input varies in a random manner D. all of the above E. none of the above...
Recent Comments