A. PERT deals with events and CPM with activities
B. critical path is determined in PERT only
C. costs are considered on CPM only and not in PERT
D. guessed times are used in PERT and evaluated times in CPM
E. PERT is used in workshops and CPM in plants
Related Mcqs:
- Product layout is employed for____________________?
- A. batch production B. continuous production C. effective utilization of machine D. all of the above E. none of the above...
- In the Halsey 50-50 plan, the following are rewarded more___________________?
- A. past good workers B. past poor workers C. past average workers D. all of the above E. none of the above...
- String diagram is used when__________________?
- A. team of workers is working at a place B. material handling is to be done C. idle time is to be reduced D. all of the above E. none of the above...
- Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
- A. consumes time, but no resources B. consumes resources but no time C. consumes neither time nor resources D. is a dangling event E. consumes both resources and time...
- In A-B-C control policy, maximum attention is given to__________________?
- A. those items which consume money B. those items which are not readily available C. those x items which are in more demand D. those items which consume more money E. proper quality assurance program-mes...
Recent Comments