.Management Sciences
A. a project will always be behind schedule, if left uncorrected
B. cost of project will always be more than the estimated cost, if no timely corrections are taken
C. a project can be subdivided into a set of predictable, independent activities
D. activities are fixed and can’t be changed ,
E. commissioning time can be changed, if activities are behind schedule
Related Mcqs:
- The term ‘value’ in value engineering refers to_______________?
- A. total cost of the product B. selling price of the product C. utility of the product D. manufactured cost of the product E. depreciation value...
- PERT has following time estimate_________________?
- A. one time estimate B. two time estimate C. three time estimate D. four time estimate E. nil time estimate...
- The main disadvantage of line organisation is_________________?
- A. top level executives have to do excessive work B. structure is rigid C. communication delays occur D. all of the above E. none of the above...
- The allowed time for a job equals standard time plus___________________?
- A. policy allowance B. interference allowance C. process allowance D. learning allowance E. unforeseen allowance...
- The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
- A. event B. free float C. artificial D. constraint E. dummy...
Recent Comments