Search
.Management Sciences
A. +ve slack
B. -ve slack
C. zero sldck
D. dummy activities
E. critical activities
Related Mcqs:
- Time study is__________________?
- A. the appraisal, in terms of time, of the value of work involving human effort B. machine setting time C. time taken by workers to do a job D. method of fixing time for workers E. method of determining the personnel Requirement...
- Standard time as compared to normal time is_______________?
- A. greater B. smaller C. equal D. there is no such correlation E. none of the above...
- The most popular type of organisation used for Civil Engineering Constructions is_________________?
- A. line organisation B. line and staff organisation C. functional organisation D. effective organisation E. none of the above...
- The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode_________________?
- A. early finish B. early start C. late start D. late finish E. none of the above...
- The reasons which are basically responsible for the formation of a queue should be that ___________________?
- A. the average service rate Hess than the average arrival rate B. output rate is linearly proportional to input C. output rate is constant and the input varies in a random manner D. all of the above E. none of the above...
Recent Comments