.Management Sciences
A. all activities should be numbered
B. only important activities should be numbered
C. only critical activities are numbered
D. only selected activities are numbered
E. no activity is numbered
Related Mcqs:
- Job evaluation is the method-of determining the________________?
- A. relative worth of jobs B. skills required by a worker C. contribution of a worker D. contribution of a job E. effectiveness of various alternatives...
- Which one of the following represents a group incentive plan ?
- A. Scanlon Plan B. Rowan Plan C. Bedaux Plan D. Taylor Differential Piece Rate System E. Halsey Premium Plan...
- The main disadvantage of line organisation is_________________?
- A. top level executives have to do excessive work B. structure is rigid C. communication delays occur D. all of the above E. none of the above...
- A milestone chart_______________________?
- A. shows the inter dependences of various jobs B. depicts the delay of jobs, if any C. points outgoing ahead of schedule of jobs, if any D. all of the above E. none of the above...
- Critical path moves along the activities having total float of_____________________?
- A. positive value B. negative value C. zero value D. same value E. none of the above...
Recent Comments