A. positive value
B. negative value
C. zero value
D. same value
E. none of the above
Related Mcqs:
- Acceptance sampling is widely used in________________?
- A. batch production B. job production C. mass production D. all of the above E. none of the above...
- In the Halsey system of wage incentive plan, a worker is ________________?
- A. paid as per efficiency B. ensured of minimum wages C. not paid any bonus till his efficiency D. never a loser E. induced to do more work...
- In steel plant the most important system for materials handling is_____________________?
- A. conveyors B. cranes and hoists C. trucks D. locos E. none of the above...
- Emergency rush order can be pushed more effectively in__________________?
- A. job production B. automatic production C. continuous production D. intermittent production E. none of the above...
- According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be___________________?
- A. HA B. HA + (S~A) HA C. HA + ^^-H D. HA + ^^-H E. HA + ^^-HA...
Recent Comments