A. 8/15
B. 7/15
C. 11/15
D. 2/11
Amount of work P can do in 1 day = 1/15
Amount of work Q can do in 1 day = 1/20
Amount of work P and Q can do in 1 day = 1/15 + 1/20 = 7/60
Amount of work P and Q can together do in 4 days = 4 × (7/60) = 7/15
Fraction of work left = 1 – 7/15= 8/15
Related Mcqs:
- A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every Third day ?
- A. 12 days B. 15 days C. 16 days D. 18 days...
- If X and Y complete a certain work in 10 days, Y and Z in 16 days and X and Z in 22 days, find the time required for each one to complete the work while working separately.
- A. 120, 40, 60 days B. 120, 60, 80 days C. 40, 30, 120 days D. 30, 40, 60 days...
- Twelve men can do a work in twenty days while twenty women can finish the same work in sixteen days. Find the ratio between the capacity of a man and a woman.
- A. 3:4 B. 5:4 C. 4:3 D. 5:3...
- A leak in the lower portion of a tank can empty the full tank in 9 hrs. An inlet pipe fills water at the rtae of 10 lit. a minute. When the tank is full, the inlet is opened and due to leak, the tank is empty in 16 hrs. How many litres does the cistern hold ?
- A. 12,342 litres. B. 12,444 litres C. 12,566 litres. D. None of thes...
- P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?
- A. 5 days B. 10 days C. 15 days D. 12 days...
Recent Comments