.Management Sciences
A. 20
B. 25
C. 125
D. 60
M1*D1*W2 = M2*D2*W1
Where, M – number of people working
D – time of work
W – number of tasks or work
6*4*W2 = 10*6*50
W2 = 125 tasks
Related Mcqs:
- A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
- A. 8 days B. 10 days C. 12 days D. 15 days...
- A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
- A. 35 Rs. B. 40 Rs. C. 45 Rs. D. None of these...
- A work can be finished in 16 days by twenty women. The same work can be finished in fifteen days by sixteen men. The ratio between the capacity of a man and a woman is_________?
- A. 1:3 B. 4:3 C. 2:3 D. 2:1...
- A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ?
- A. 40 days B. 50 days C. 60 days D. 70 days...
- If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct it is :
- A. 12 days B. 14 days C. 16 days D. 18 days...
Recent Comments