.Management Sciences
A. 1
B. 5
C. 10
D. 25
10 workers make 10 tables in 10 days. 1 worker makes 1 table in 10 days. Similarly, 5 workers can make 5 tables in 10 days.
Related Mcqs:
- A and B can do a piece of work in 72 days; B and C can do it in 120 days; A and C can do it in 90 days. In what time can A alone do it ?
- A. 80 days B. 100 days C. 120 days D. 150 days...
- A can do a particular work in 6 days . B can do the same work in 8 days. A and B signed to do it for Rs. 3200. They completed the work in 3 days with the help of C. How much is to be paid to C?
- A. Rs. 380 B. Rs. 600 C. Rs. 420 D. Rs. 400...
- P is 30% more efficient than Q. P can complete a work in 23 days. If P and Q work together, how much time will it take to complete the same work?
- A. 9 B. 11 C. 23 D. 13...
- Kamal will complete work in 20 days. If Suresh is 25% more efficient than Kamal, he can complete the work in________days.
- A. 14 B. 16 C. 15 D. 11...
- Two taps X and Y can fill a tank in 10 hrs. and 15 hrs.respectively. If the both taps are opened together, the tank will be full in_________?
- A. 3 hrs. B. 4 hrs, C. 5 hrs. D. 6 hrs....
Recent Comments