A. 37 ½ days
B. 22 days
C. 31 days
D. 22 days
Work done by A in 20 days = 80/100 = 8/10 = 4/5
Work done by A in 1 day = (4/5) / 20 = 4/100 = 1/25 — (1)
Work done by A and B in 3 days = 20/100 = 1/5 (Because remaining 20% is done in 3 days by A and B)
Work done by A and B in 1 day = 1/15 —(2)
Work done by B in 1 day = 1/15 – 1/25 = 2/75
=> B can complete the work in 75/2 days = 37 ½ days
Related Mcqs:
- B can work 3 times faster than A. They work together on a task and complete it in a day. How long does it take for B alone to complete the task?
- A. 32 hours B. 48 hours C. 3 days D. 4 days...
- A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
- A. 35 Rs. B. 40 Rs. C. 45 Rs. D. None of these...
- If 10 bulls can plough 20 identical fields in 3 days working 10 hours a day, then in how many days can 30 bulls plough 32 same identical fields working 8 hours a day?
- A. 2 B. 8 C. 10 D. 12...
Recent Comments