A. 70
B. 50
C. 40
D. 60
Amount of work done by A and B in 1 day = 1/30
Amount of work done by A and B in 20 days = 20 × (1/30) = 20/30 = 2/3
Remaining work – 1 – 2/3 = 1/3
A completes 1/3 work in 20 days
Amount of work A can do in 1 day = (1/3)/20 = 1/60
=> A can complete the work in 60 days
Related Mcqs:
- Two pipes can fill a tank in 10 hrs. and 12 hrs. respectively while a third pipe empties the full tank in 20 hrs. If all the three pipes operate together , in how much time the tank will be filled ?
- A. 7.5 hrs B. 5 hrs C. 7 hrs D. None of these...
- If two pipes function together, the cistern will be filled in 6 hrs. One pipe fills the cistern 5 hrs. faster than the other. How many hours it take the second pipe to fill the cistern?
- A. 5 hrs B. 10 hrs C. 15 hrs D. 20 hrs...
- If 6 men working together can complete 50 identical tasks in 4 hours then how many such identical tasks can be completed if 10 men are working together for 6 hours?
- A. 20 B. 25 C. 125 D. 60...
- P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
- A. 7 B. 8 C. 9 D. 10...
- Two taps X and Y can fill a tank in 10 hrs. and 15 hrs.respectively. If the both taps are opened together, the tank will be full in_________?
- A. 3 hrs. B. 4 hrs, C. 5 hrs. D. 6 hrs....
Recent Comments