A. 12
B. 8
C. 10
D. 9
Part of work completed by A in a day = 1/X Part of work completed by B in a day
= 1/(X+5) (1/X)+(1/(X+5)) = 1/6 (2X+5)/(X²+5X) = 1/6 X²+5X = 6(2X+5) X²-7X-30=0 Solving, X=10
Related Mcqs:
- 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
- A. 15 days B. 10 days C. 8 days D. 20 days...
- A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
- A. 35 Rs. B. 40 Rs. C. 45 Rs. D. None of these...
- If 10 bulls can plough 20 identical fields in 3 days working 10 hours a day, then in how many days can 30 bulls plough 32 same identical fields working 8 hours a day?
- A. 2 B. 8 C. 10 D. 12...
- P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?
- A. 10 days B. 14 days C. 15 days D. 9 days...
Recent Comments