.Management Sciences
A. 12 days
B. 16 days
C. 18 days
D. 20 days
Related Mcqs:
- A and B can do a piece of work in 72 days; B and C can do it in 120 days; A and C can do it in 90 days. In what time can A alone do it ?
- A. 80 days B. 100 days C. 120 days D. 150 days...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- If 6 men working together can complete 50 identical tasks in 4 hours then how many such identical tasks can be completed if 10 men are working together for 6 hours?
- A. 20 B. 25 C. 125 D. 60...
- P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
- A. 8/15 B. 7/15 C. 11/15 D. 2/11...
- P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?
- A. 5 days B. 10 days C. 15 days D. 12 days...
Recent Comments