A _______________ is developed using historical cost information that relates some software metric to the project cost ?
A. Algorithmic cost modelling
B. Expert judgement
C. Estimation by analogy
D. Parkinson’s Law
(more…)
Which of the following costs is not part of the total effort cost ?
A. Costs of networking and communications
B. Costs of providing heating and lighting office space
C. Costs of lunch time food
D. Costs of support staff
(more…)
Which of the following is/are main parameters that you should use when computing the costs of a software development project ?
A. travel and training costs
B. hardware and software costs
C. effort costs (the costs of paying software engineers and managers)
D. all of the mentioned
(more…)
Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks ?
A. Software Macroscopic schedule
B. Software Project scheduling
C. Software Detailed schedule
D. None of the mentioned
Which paradigm relies on the natural compartmentalization of a problem and organizes team members to work on pieces of the problem with little active communication among themselves ?
A. random paradigm
B. open paradigm
C. closed paradigm
D. synchronous paradigm
Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system ?
A. System building
B. Release management
C. Change management
D. Version management
Commitments to unrealistic time and resource estimates may result in____________________?
A. project delay
B. poor quality work
C. project failure
D. all of the mentioned
A technique for performing quantitative analysis of progress is known as______________________?
A. BCWS
B. EVA
C. BAC
D. CBSE
(more…)
Which model is used during early stages of the system design after the requirements have been established ?
A. An application-composition model
B. A post-architecture model
C. A reuse model
D. An early design model
(more…)
Which of the following option is not tracked by configuration management tools ?
A. Tracking of change proposals
B. Storing versions of system components
C. Tracking the releases of system versions to customers
D. None of the mentioned