What does symbol ‘O’ imply in work study________________?
A. operation
B. inspection
C. transport
D. delay/temporary storage
E. none of the above
Material handling and plant location is analysed by________________?
A. Gnatt chart
B. bin chart
C. Emerson chart
D. travel chart
E. activity chart
The two-bin system is concerned with_________________?
A. ordering procedure
B. forecasting sales
C. production planning
D. despatching and expediting
E. none of the above
Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above
Micromotion study involves following number of fundamental hand motions_______________?
A. 8
B. 12
C. 16
D. 20
E. 24
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
A. duration
B. total float
C. free float
D. interfering float
E. none of the above
Which of the following organisation is preferred in automobile industry________________?
A. functional organisation
B. line organisation
C. staff organisation
D. line and staff organisations
E. scalar organisation
The amount deducted from the salary of workers towards employees provident fund is_______________?
A. credited into reserves of company
B. deposited in nationalised bank
C. deposited in post office
D. deposited in the account of worker with employer or Reserve Bank of India
E. deposited in the account of worker with Provident Fund Commissioner
The technique of value analysis can be applied to____________________?
A. complicated items only
B. simple items only
C. crash programmer items only
D. cost consciousness items only
E. any item