Category: Production Technology
The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as_________________?
A. Dry work Plan
B. Halsey Premium Plan
C. Taylor Plan
D. Bedaux Plan
E. Rowan Plan
Current assets include_______________?
A. manufacturing plant
B. manufacturing plant and equipment
C. inventories
D. common stock held by the firm
E. all of the above
PERT and CPM are__________________?
A. techniques to determine project status
B. decision making techniques
C. charts which increase aesthetic appearance of rooms
D. aids to determine cost implications of project
E. aids to the decision maker
The critical activity has____________________?
A. maximum float
B. minimum float
C. zero float,
D. average float
E. none of these
Which of the following equations is not in conformity with others______________?
A. organisation performance x motivation = profits
B. knowledge x skill = ability
C. ability x motivation = performance
D. attitude x situation = motivation
E. performance x resources
PERT is the__________________?
A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique
The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as_________________?
A. Rowan Plan
B. Bedaux Plan
C. Taylor Differential Piece rate system
D. Halsey Premium plan
E. Day work plan
CPM is the___________________?
A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique
The disadvantage of product layout is_________________?
A. high initial investment for the specialized facilities
B. skilled labour to operate machines
C. production time is longer, requiring more goods in inventory
D. high cost of inspection
E. costly and complex production control
The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
A. event
B. free float
C. artificial
D. constraint
E. dummy