Pick up the incorrect statement from the following?
A. an activity of the project is denoted by an arrow on the net work
B. the tail of the arrow indicates the start of the activity
C. the head of the arrow indicates the end of,the activity!
D. the arrows are drawn (to scale from) left to right
E. each activity consumes a given time
Inventory management consists of__________________?
A. effective running of stores
B. state of merchandise methods of stroing and maintenance etc
C. stock control system
D. all of the above
E. none of the above
According to MAPI formula, the old machine should be replaced by new one when_____________?
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. there is no such criterion
E. none of the above
(CAM = Challenger’s Adverse minimum DAM = Defender’s Adverse minimum)
Expediting function consists in keeping a watch on__________________?
A. operator’s activity
B. flow of material and in case of trouble locate source of trouble
C. minimising the delays
D. making efficient despatching
E. none of the above
The standard time for a job is_________________?
A. total work content
B. base time + relaxation time
C. total work content + basic time
D. total work content + delay contingency allowance
E. total work content + relaxation time
In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches__________________?
A. 50%
B. 661%
C. 75%
D. 80%
E. 90%
Standing orders which are statutory are applicable to__________________?
A. all industries
B. all process industries and thermal power plants
C. only major industries
D. only key industries
E. all industries employing more than 100 workers
PERT has following time estimate_________________?
A. one time estimate
B. two time estimate
C. three time estimate
D. four time estimate
E. nil time estimate
Standard time as compared to normal time is_______________?
A. greater
B. smaller
C. equal
D. there is no such correlation
E. none of the above
String diagram is used when__________________?
A. team of workers is working at a place
B. material handling is to be done
C. idle time is to be reduced
D. all of the above
E. none of the above