The assumption in PERT is__________________?

A. a project will always be behind schedule, if left uncorrected
B. cost of project will always be more than the estimated cost, if no timely corrections are taken
C. a project can be subdivided into a set of predictable, independent activities
D. activities are fixed and can’t be changed ,
E. commissioning time can be changed, if activities are behind schedule

Pick up the correct statement from the following?

A. the float may be positive, zero or negative
B. if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
C. if the float of an activity is negative, delay in its performance is bound to delay the completion of project
D. if the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
E. all of the above