Category: Time and Work Mcqs
A and B can do a piece of work in 12 days; B and C in 15 days; C and A in 20 days. A alone can do the work in__________?
0
A. 20 days
B. 30 days
C. 40 days
D. none of these
If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?
A. 2 men
B. 12 men
C. 9 men
D. 18 men
(more…)
A is thrice as good a work man as B and takes 10 days less to do a piece of work than B takes. B can do the work in:___________?
A. 15 days
B. 14 days
C. 16 days
D. 30 days
(more…)