In sewers designed with self cleansing velocity________________?
A. The bottom is silted
B. The bottom is scoured
C. Both silting and scouring occur at the bottom
D. Neither silting nor scouring occurs at the bottom
Pick up the correct statement from the following ?
A. Small sewers are cleaned by flushing
B. Medium sewers are cleaned by cane rodding
C. Medium sewers may be cleaned by pills
D. All the above
Removal of oil and grease from sewage, is known____________________?
A. Screening
B. Skimming
C. Filtration
D. None of these
The sewerage system consists of______________________?
A. House sewer
B. Lateral sewer
C. Branch sewer
D. All of these
The sewer that unloads the sewage at the point of treatment is called_________________?
A. Main sewer
B. Outfall sewer
C. Branch sewer
D. House sewer
In sewers the highest non-scouring velocity is achieved in________________?
A. Glazed bricks sewers
B. Cast iron sewers
C. Cement concrete sewers
D. Stone ware sewers
In olden days the type of section adopted in trunk and out fall sewers was__________________?
A. Parabolic shaped
B. Horse shoe shaped
C. Egg shaped
D. Circular shaped
To prevent settling down of sewage both at the bottom and on the sides of a large sewer, self-cleaning velocity recommended for Indian conditions, is_________________?
A. 0.50 m/sec
B. 0.60 m/sec
C. 0.70 m/sec
D. 0.75 m/sec
Pick up the correct statement from the following?
A. The maximum rate of storm runoff is called peak drainage discharge
B. Rational method of estimating peak run off, may be used precisely for areas less than 50 hectares
C. The period after which the entire area starts contributing to the runoff, is called the time of concentration
D. All the above
In a grit chamber of a sewage treatment plant ____________________?
A. Flow velocity 0.15 m to 0.3 m/sec is kept
B. Depth of 0.9 m to 1.20 m is kept
C. One minute of detention period is kept
D. All the above