Crash project duration is obtained by summing the________________?
A. normal durations for all the activities
B. crash durations for all activities
C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
If the dynamic viscosity of a fluid is 0.5 poise and specific gravity is 0.5, then the kinematic viscosity of that fluid in stokes is__________________?
A. 0.25
B. 0.50
C. 1.0
D. none of the above
The ratio of minimum hourly flow to the average flow of sewage is_________________?
A. 1/4
B. 1/3
C. 1/2
D. 3/4