Benchmark is established by________________?
A. hypsometry
B. barometric levelling
C. spirit levelling
D. trigonometrical levelling
Crash project duration is obtained by summing the________________?
A. normal durations for all the activities
B. crash durations for all activities
C. crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
If the dynamic viscosity of a fluid is 0.5 poise and specific gravity is 0.5, then the kinematic viscosity of that fluid in stokes is__________________?
A. 0.25
B. 0.50
C. 1.0
D. none of the above
The ratio of minimum hourly flow to the average flow of sewage is_________________?
A. 1/4
B. 1/3
C. 1/2
D. 3/4
The arrangement made for passing the sewer line below an obstruction below the hydraulic gradient lines called ____________________?
A. Inverted syphon
B. Depressed sewer
C. Sag pipe
D. all of these
The height of the rail for 52 kg rail section is_______________?
A. 143 mm
B. 156 mm
C. 172 mm
D. 129mm