Pick up the correct statement from the following?
A. Bricks are paid per thousand
B. Cement is paid per 50 kg bag
C. Lime is paid per quintal
D. All the above
Pick up the correct statement from the following?
A. The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value
B. The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost
C. The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval
D. All the above
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is____________________?
A. 3250 m3
B. 3225 m3
C. 3275 m3
D. 3300 m3
The assumption on which the trapezoidal formula for volumes is based, is________________?
A. The end sections are parallel planes
B. The mid-area of a pyramid is half the average area of the ends
C. The volume of the Prismoidal is over-estimated and hence a Prismoidal correction is applied
D. All the above
The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm
The floor area includes the area of the balcony up to_________________?
A. 100 %
B. 75 %
C. 50 %
D. 25 %
Pick up the correct statement from the following?
A. In order to check up the average depth of excavation, ‘Dead man s’ are left at the mid-widths of borrow pits
B. The earthwork calculation in excavation is made from the difference in levels obtained with a level
C. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
D. All the above
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds_________________?
A. 2.0 %
B. 2.5 %
C. 4.0 %
D. 5.0 %
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
A. 0.90 m3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3