The temperature reinforcement in the vertical slab of a T-shaped R.C. retaining wall is______________?
A. not needed
B. provided equally on inner and front faces
C. provided more on inner face than on front face
D. provided more on front face than on inner face
The compressive strength of 100 mm cube as compared to 150 mm cube is always_______________?
A. less
B. more
C. equal
D. none of the above
If the depth of neutral axis for a singly reinforced rectangular section is represented by kd in working stress design, then the value of k for balanced section_______________?
A. depends on as, only
B. depends on aCbC only
C. depends on both crst and acbc
D. is independant of both ast and acbc where d is the effective depth, ast is per-missible stress in steel in tension and ocbc is permissible stress in concrete in bend¬ing compression
Select the incorrect statement?
A. The loss of prestress is more in pre-tensioning system than in post-tensioning system.
B. Pretensioning system has greater certainty about its durability.
C. For heavy loads and large spans in buildings or bridges, post-tensioning system is cheaper than pretensioning system
D. none of the above
In T-shaped R C. retaining walls, the main reinforcement in the stem is provided on______________?
A. the front face in one direction
B. the front face in both directions
C. the inner face in one direction
D. the inner face in both directions
The main reinforcement in the toe of a T- shaped R C. retaining wall is provided on_______________?
1. top face parallel to the wall
2. top face perpendicular to the wall
3. bottom face paralleUo the wall
4. bottom face perpendicular to the wall
The correct answer is ?
A. only (2) is correct
B. (1) and (2)are correct
C. (3) and (4) are correct
D. only (4) is correct
Admixtures which cause early setting, and hardening of concrete are called_______________?
A. workability admixtures
B. accelerators
C. retarders
D. air entraining agents
The limits of percentage p of the longitudinal reinforce-ment in a column is given by_____________?
A. 0.15% to 2%
B. 0.8% to 4%
C. 0.8% to 6%
D. 0.8% to 8%
The purpose of reinforcement in prestressed concrete is________________?
A. to provide adequate bond stress
B. to resist tensile stresses
C. to impart initial compressive stress in concrete
D. all of the above
In a pile of length /, the points of suspension from ends for lifting it are located at______________?
A. 0.207 1
B. 0.25 /
C. 0.293 /
D. 0.333 /