1. The construction of the building now to cost P 400,000
2. The construction of a smaller building now to cost P300,000 and at the end of 5 years, an extension to be added to cost P 200,000.
By how much is proposal B more economical than proposal A if interest rate is 20% and depreciation to be neglected ?
A. P 19,122.15
B. P 19,423.69
C. P 19,518.03
D. P 19,624.49
Related Mcqs:
- “When one of the factors of production is fixed in quantity or is difficult to increase, increasing the other factors of production will result in a less than proportionate increase in output”. This statement is known as the______________?
- A. Law of diminishing return B. Law of supply C. Law of demand D. Law of supply and demand...
- What market situation exists where there are few sellers and few buyers ?
- A. Oligopoly B. Oligopsony C. Bilateral oligopoly D. Bilateral Oligopsony...
- You borrow P3,500.00 for one year from a friend at an interest rate of 1.5% per month instead of taking a loan from a bank at a rate of 18% per year. How much lesser you will pay by borrowing the money from the bank ?
- A. P 62.44 B. P44.55 C. P54.66 D. P37.56...
- What method is often used in municipal project evaluations where benefits and costs accrue to different segments of the community ?
- A. Annual cost method B. Benefit-cost ratio C. Rate of return method D. EUAC...
- What is defined as the current assets minus inventories and prepaid expenses ?
- A. Profit margin ratio B. Price-earnings ratio C. Return of investment ratio D. Quick ratio...
Recent Comments