Search
.Management Sciences
A. site investigation started
B. sessional work completed
C. bus starts from Jaipur
D. class is being attended
Related Mcqs:
- The normal time required for the completion of project in the above problem is_______________?
- A. 9 days B. 13 days C. 14 days D. 19 days...
- In resources levelling________________?
- A. total duration of project is reduced B. total duration of project is increased C. uniform demand of resources is achieved D. cost of project is controlled...
- The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
- A. Rs. 8,800/- B. Rs. 7,600/- C. Rs. 6,400/- D. Rs. 5,000/-...
- An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is__________________?
- A. Rs. 8,43,750/- B. Rs. 8,75,000/- C. Rs. 10,50,000/- D. Rs. 11,56,250/-...
- Free float is mainly used to_________________?
- A. identify the activities which can be delayed without affecting the total float of preceding activity B. identify the activities, which can be delayed without affecting the total float of succeeding activity C. establish priorities D. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities...