Search
.Management Sciences
A. change of critical path
B. decrease of project completion time
C. increase of project completion time
D. all of the above
Related Mcqs:
- The normal time required for the completion of project in the above problem is_______________?
- A. 9 days B. 13 days C. 14 days D. 19 days...
- A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be________________?
- A. 3.7 years B. 4.23 years C. 5 years D. 7.87 years...
- Wheeled tractors are replacing crawler tractors because________________?
- Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control A. 1,3 and 4 are correct B. 2, 3 and 4 are correct C. 1,2 and 3 are correct D. 1, 2 and 4 are … Wheeled tractors are replacing crawler tractors because________________?Read More...
- If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?
- A. 2.3% and 84.1% B. 97.7% and 84.1% C. 97.7 % and 15.9% D. 15.9% and 97.7%...