.Management Sciences
A. its latest finish time and earliest start time for its successor activity
B. its latest start time and earliest start time
C. its latest start time and earliest finish time
D. its earliest finish time and earliest start time for its successor activity
Related Mcqs:
- The normal time required for the completion of project in the above problem is_______________?
- A. 9 days B. 13 days C. 14 days D. 19 days...
- In resources levelling________________?
- A. total duration of project is reduced B. total duration of project is increased C. uniform demand of resources is achieved D. cost of project is controlled...
- The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
- A. Rs. 8,800/- B. Rs. 7,600/- C. Rs. 6,400/- D. Rs. 5,000/-...
- An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is__________________?
- A. Rs. 8,43,750/- B. Rs. 8,75,000/- C. Rs. 10,50,000/- D. Rs. 11,56,250/-...
- If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
- A. 3.5 and 5/6 B. 5 and 25/36 C. 3.5 and 25/36 D. 4 and 5/6...