.Management Sciences
A. crash time
B. normal time
C. optimistic time
D. standard time
Related Mcqs:
- Rolling resistance of a wheel depends upon_____________?
- (i) Vehicle load (ii) Grade (iii) Ground select the correct statements? A. only (i) is correct B. (i) and (ii) are correct C. (i) and (iii) are correct D. (ii) and (iii) are correct...
- Wheeled tractors are replacing crawler tractors because________________?
- Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control A. 1,3 and 4 are correct B. 2, 3 and 4 are correct C. 1,2 and 3 are correct D. 1, 2 and 4 are … Wheeled tractors are replacing crawler tractors because________________?Read More...
- Sensitivity analysis is a study of__________________?
- A. comparison of profit and loss B. comparison of assets and liabilities C. change in output due to change in input D. economics of cost and benefits of the project...
- If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
- A. 50% B. less than 50% C. more than 50% D. 100%...
- Economic saving of time results by crashing_________________?
- A. cheapest critical activity B. cheapest non-critical activity C. costliest critical activity D. costliest non-critical activity...
Recent Comments