.Management Sciences
A. total float
B. free float
C. interfering float
D. independent float
Related Mcqs:
- The time corresponding to minimum total project cost is_______________?
- A. crash time B. normal time C. optimistic time D. between normal time and crash time...
- A machine is purchased for Rs. 10,000,00/- and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000/-. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is__________________?
- A. Rs. 4,75,000/- B. Rs. 5,75,000/- C. Rs. 6,50,000/- D. Rs. 8,50,000/-...
- Wheeled tractors are replacing crawler tractors because________________?
- Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control A. 1,3 and 4 are correct B. 2, 3 and 4 are correct C. 1,2 and 3 are correct D. 1, 2 and 4 are … Wheeled tractors are replacing crawler tractors because________________?Read More...
- In time-cost optimization of a project, crashing is done____________?
- A. on all the activities B. on all the activities lying on the critical path C. only on activities lying on the orginal critical path and having flatter cost slopes D. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope...
- The time with which direct cost does not reduce with the increase in time is known as_________________?
- A. crash time B. normal time C. optimistic time D. standard time...
Recent Comments