A. decreasing the direct cost and increasing indirect cost
B. increasing the direct cost and decreasing the indirect cost
C. increasing the direct cost and indirect cost both
D. decreasing the direct cost and indirect cost both
Related Mcqs:
- Critical path_____________?
- A. is always longest B. is always shortest C. may be longest D. may be shortest...
- A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be________________?
- A. 3.7 years B. 4.23 years C. 5 years D. 7.87 years...
- For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________?
- A. 8 days B. 9 days C. 10 days D. 15 days...
- Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
- A. Ice B. Concrete C. Loose sand D. Earth...
- Free float for any activity is defined as the difference between__________________?
- A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time C. its latest finish time and earliest start time for its successor activity D. its earliest finish time and latest start time for its successor activity...
Recent Comments