A. Smooth-wheeled rollers
B. Vibratory rollers
C. Sheep foot rollers
D. Tampers
Related Mcqs:
- Which of the following does not represent an activity?
- A. site located B. foundation is being dug C. the office area is being cleaned D. the invitations are being sent...
- Which of the following excavators is most suitable for digging under water?
- A. Drag line B. Hoe C. Clam shell D. Dipper shovel...
- In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
- A. longest duration B. highest cost slope C. least cost slope D. shortest duration...
- In the bar chart planning____________?
- Consider the following statements? 1. interdependence of the operations cannot be portrayed 2. progress of work can be measured 3. spare time of the activities can be determined 4. schedule cannot be updated A. 1,2 and 3 are correct B. 1 and 4 are correct C. 2, 3 and 4 are correct D. 1,2 and … In the bar chart planning____________?Read More...
- Total float for any activity is defined as the difference between________________?
- A. its latest finish time and earliest start time for its successor activity B. its latest start time and earliest start time C. its latest start time and earliest finish time D. its earliest finish time and earliest start time for its successor activity...